Northeast Interceptor-Truax Extension Project

Project Status:  Design
The new sewer line, which will run from Lien Road to the intersection of Highway 51 and Rieder Road, will increase capacity and boost resiliency of the district’s wastewater collection system.

Selected Route
                           

 

Project will boost capacity, build resilience
The existing 48" pipe was constructed in 1969.  Inspection of the pipe in 2011 identified corrosion of the interior concrete surface. The existing pipe is also nearing capacity. To meet future anticipated growth, either a bigger pipe (called a replacement sewer) or a second pipe (called a relief sewer) working in parallel with the existing pipe is required.

The project currently under consideration is the relief sewer option. Once the relief sewer is completed, the district intends to rehabilitate the existing pipe by inserting a new lining to protect against further corrosion. This construction strategy reduces risks and total project costs because building the relief sewer first minimizes the need for costly bypass pumping during construction. And ultimately, operating two sewer lines will enhance the resilience of the collection system.  

Four different routes were presented on May 30, 2018 at a public meeting.  Residents, members of the business community and property owners in attendance at the meeting provided feedback on the alternatives.  The alternatives analysis was completed in June 2018, and Alternative 3 is the recommended route for the relief sewer.  Alternative 3, which runs along the west edge of Reindal Park, was presented and approved by the City of Madison Parks Board at their June 13, 2018 meeting.  

It will be a big dig
When the project gets underway in 2019, it will involve tunneling under East Washington Avenue and excavating at depths exceeding 25 feet.  Traffic will be impacted on Lien Road between Parkside Drive and Thierer Road. The District is working with Strand Associates on the design and expects to bid the project in January/February of 2019 with construction from summer of 2019 to early spring of 2020. 

For questions, contact Jen Hurlebaus, Madison Metropolitan Sewerage District project manager, jenh@madsewer.org or 608-222-1201 ext 248.