
Protecting
public health and the environment

What's New
|
|
|
|
|
District Response to June
2008 High Flow Events
The Madison Metropolitan Sewerage
District, along with other municipalities in southern Wisconsin,
is recovering from the extraordinary precipitation events and
subsequent flooding that took place in early June. The District
measured its all-time high peak flow rate of 100,000 gallons per
minute and its all-time high one-day wastewater volume of 106
million gallons on June 9. Typical volumes during periods of
normal weather are about 40 million gallons per day.
The high flows resulted from rain water that leaked into
basements and rain water that flooded streets and low areas and
leaked into manholes and through defects in sewer lines. The
excess flow from these sources overwhelmed the District’s
conveyance system for a period of about 30 hours on June 8 and
9. Even though all pumping equipment was available and in
operation during this entire event, many homes and businesses
experienced basement back-ups from the sewer system. The
District employed portable pumping equipment at two pumping
stations to remove water from the sewer system and prevent
further basement backups. Even so, the sewer system overflowed
from manholes at several points. System overflows and the
portable pump discharges ultimately reached nearby wetlands,
streams, and the lakes.
Over the past fifteen years the District has experienced six or
more significant storm events that have led to high flows in the
sewer system. Many scientists now expect that storms of higher
intensity and longer duration will be experienced more
frequently in the future. To address this possibility and to
lessen the likelihood of future events overwhelming the sewer
system, the Madison Metropolitan Sewerage District is taking the
following actions:
|
1. |
The District is
reviewing its design standards for sizing
interceptor sewers and pumping stations. The
District currently provides an allowance for high
flows in these facilities that varies from peak flow
capacities 4.0 times greater than the average daily
flows for facilities with average day design flows
of one million gallons per day to peak flow
capacities 2.5 times greater than the average daily
flows for facilities with average day design flows
of 20 million gallons per day. The review will
include data from the storm events of the past
fifteen years. If higher peaking factors are judged
to be necessary, the schedule for construction of
replacement interceptor sewers and pumping stations
will need to be accelerated, and new and replaced
facilities will be larger. This will lessen the
likelihood of back-ups and overflows and will result
in higher costs for service. |
| |
|
|
2. |
The District is
reviewing its design standards for materials used in
constructing interceptor sewers, including manholes,
to assure that rain waters are less likely to leak
into these facilities during heavy rains and floods. |
| |
|
|
3. |
The District is
reviewing flow data and inspecting its existing
interceptor sewers to identify and repair defects
that allowed excessive rain water leakage into the
District’s system. |
| |
|
|
4. |
The District is
reviewing flow data from its customer communities
collected during the recent high flow events. This
review will identify likely areas in community sewer
systems that experienced excessive leakage during
the recent high flow events. The District will work
with these communities to address these areas. |
| |
|
|
5. |
The District will
make greater efforts to educate the public in the
area of water conservation and how to prevent rain
water from leaking into basements. Water
conservation and reduced inflow will have positive
impacts in both dry and wet weather. |
Although the events of June
were unprecedented, this will not be the last challenge of this
type that we will face. The District is taking action now to
better insure that future events will have less impact on the
public and the environment. |
|
|
|
 |
Mercury Pollutant Minimization Program
Dental Amalgam BMPs Training Videos 1-4
Dental sector achieves 60%
installation rate.
Click here
to go to the
mercury page. |
|
|
|
|
|
MMSD Master Planning Project Presentations
District staff will be making brief presentations regarding the
master planning project at several of our customer communities’
regularly scheduled monthly meetings. The presentations will
include the following topics:
-
Background information on the District and it’s challenges
-
The master planning process and schedule
-
Future opportunities for the public to provide input to the
planning process
District personnel and our consultants will be available to
answer questions and listen to the thoughts and ideas presented
by the meeting attendees. To-date, we have 7 presentations
scheduled in the months of February and March.
Click here
for a list of currently
scheduled meetings. |
|
|
|
|
|
Visions Goals and
Strategies updated
The District recently updated its
strategic plan, which is described in the Vision, Goals and
Strategies (VGS) document. Click
here for the most recent edition of the VGS document. |
|
|
|
Web Policies