| Estimated | R.G. Huston | McHugh Construction | Capitol Underground | Super Excavators | Speedway Sand & Gravel | |||||||||||||
| Bid Item | Quantity | Unit | Cost/Unit | Total Cost | Cost/Unit | Total Cost | Cost/Unit | Total Cost | Cost/Unit | Total Cost | Cost/Unit | Total Cost | ||||||
| 1 | Traffic Control | 1 | ea | $35,491.00 | $35,491.00 | $10,000.00 | $10,000.00 | $27,000.00 | $27,000.00 | $15,000.00 | $15,000.00 | $10,000.00 | $10,000.00 | |||||
| 2 | Clearing and Grubbing | 1 | ea | $4,308.00 | $4,308.00 | $4,180.00 | $4,180.00 | $4,600.00 | $4,600.00 | $4,000.00 | $4,000.00 | $5,000.00 | $5,000.00 | |||||
| 3 | Remove and Replace Guard Rail | 350 | LF | $8.00 | $2,800.00 | $7.25 | $2,537.50 | $9.50 | $3,325.00 | $7.00 | $2,450.00 | $10.00 | $3,500.00 | |||||
| 4 | Sawcut Asphalt Pavement | 280 | LF | $1.50 | $420.00 | $1.00 | $280.00 | $3.00 | $840.00 | $1.00 | $280.00 | $2.00 | $560.00 | |||||
| 5 | Sawcut Concrete Pavement | 90 | LF | $2.50 | $225.00 | $2.00 | $180.00 | $5.00 | $450.00 | $2.00 | $180.00 | $3.00 | $270.00 | |||||
| 6 | Construction Barrier Fence | 2,500 | LF | $1.76 | $4,400.00 | $1.65 | $4,125.00 | $1.80 | $4,500.00 | $2.00 | $5,000.00 | $2.00 | $5,000.00 | |||||
| 7 | Utility Line Opening (ULO) | 3 | ea | $1,031.00 | $3,093.00 | $450.00 | $1,350.00 | $475.00 | $1,425.00 | $1,500.00 | $4,500.00 | $700.00 | $2,100.00 | |||||
| 8 | Bypass Pumping & Temporary Connections | 1 | ea | $58,526.00 | $58,526.00 | $23,500.00 | $23,500.00 | $8,500.00 | $8,500.00 | $75,000.00 | $75,000.00 | $76,000.00 | $76,000.00 | |||||
| 9 | 36" Epoxy-Lined DI, Pressure Class 200 | 2,606 | LF | $205.00 | $534,230.00 | $283.00 | $737,498.00 | $336.00 | $875,616.00 | $280.00 | $729,680.00 | $375.00 | $977,250.00 | |||||
| 10 | 24" Epoxy-Lined DI, Pressure Class 200 | 246 | LF | $144.00 | $35,424.00 | $128.75 | $31,672.50 | $99.00 | $24,354.00 | $150.00 | $36,900.00 | $112.00 | $27,552.00 | |||||
| 11 | Low Pressure Air Leakage Tests | 1 | ea | $10,147.00 | $10,147.00 | $8,850.00 | $8,850.00 | $3,500.00 | $3,500.00 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | |||||
| 12 | 18" Cement-Lined DI, Pressure Class 250 | 12 | LF | $414.00 | $4,968.00 | $331.00 | $3,972.00 | $100.00 | $1,200.00 | $550.00 | $6,600.00 | $500.00 | $6,000.00 | |||||
| 13 | 10" Cement-Lined DI, Pressure Class 350 | 10 | LF | $200.00 | $2,000.00 | $148.00 | $1,480.00 | $90.00 | $900.00 | $370.00 | $3,700.00 | $300.00 | $3,000.00 | |||||