| MICHELS CORP. | VISU-SEWER | INSITUFORM | MCCANN | LAMETTI | ||||||||||||||
| UNIT OF | UNIT | EXTENDED | UNIT | EXTENDED | UNIT | EXTENDED | UNIT | EXTENDED | UNIT | EXTENDED | ||||||||
| ITEM | DESCRIPTION | QUANT | MEASURE | PRICE | AMOUNT | PRICE | AMOUNT | PRICE | AMOUNT | PRICE | AMOUNT | PRICE | AMOUNT | |||||
| 1 | Furnish & Install 54" CIPP | 420 | Linear Foot | $ 522.00 | $ 219,240.00 | $ 855.00 | $359,100.00 | $ 710.00 | $298,200.00 | $ 598.40 | $251,328.00 | $ 615.00 | $258,300.00 | |||||
| 2 | Furnish & Install 54" CIPP | 40 | Linear Foot | $ 975.00 | $ 39,000.00 | $ 4,687.00 | $187,480.00 | $ 1,750.00 | $ 70,000.00 | $ 598.40 | $ 23,936.00 | $ 615.00 | $ 24,600.00 | |||||
| 3 | Furnish & Install 54" CIPP | 10 | Linear Foot | $ 485.00 | $ 4,850.00 | $ 550.00 | $ 5,500.00 | $ 850.00 | $ 8,500.00 | $ 598.40 | $ 5,984.00 | $ 200.00 | $ 2,000.00 | |||||
| 4 | Furnish & Install Manhole | 1 | Lump Sum | $62,275.00 | $ 62,275.00 | $70,000.00 | $ 70,000.00 | $63,000.00 | $ 63,000.00 | $79,600.00 | $ 79,600.00 | $73,000.00 | $ 73,000.00 | |||||
| 5 | Select Sand Backfill | 150 | CY | $ 9.00 | $ 1,350.00 | $8.50 | $ 1,275.00 | $40.00 | $ 6,000.00 | $14.00 | $ 2,100.00 | $ 14.00 | $ 2,100.00 | |||||
| 6 | Pavement Restoration | 150 | SY | $ 38.00 | $ 5,700.00 | $38.00 | $ 5,700.00 | $70.00 | $ 10,500.00 | $49.00 | $ 7,350.00 | $ 49.00 | $ 7,350.00 | |||||
| 7 | Curb & Gutter Restoration | 80 | Linear Foot | $ 28.00 | $ 2,240.00 | $27.00 | $ 2,160.00 | $60.00 | $ 4,800.00 | $40.00 | $ 3,200.00 | $ 40.00 | $ 3,200.00 | |||||
| TOTAL BID = | - | $ 334,655.00 | - | $631,215.00 | - | $461,000.00 | - | $373,498.00 | $370,550.00 | |||||||||