| R.G. Huston Company, Inc. | Hammersley Stone Co. Inc. | McHugh Excavating & | E & N Hughs Co. Inc. | Capitol Underground, Inc. | Super Excavators, Inc. | |||||||||||
| 2561 Coffeytown Road | P.O. Box 44217 | Plumbing, Inc. | N2629 Coplien Road | 2413 Parmenter Street | N59 W14601 Bobolink Ave | |||||||||||
| Cottage Grove, WI 53527 | Madison, WI 53744 | W7010 Evergreen Way | Monroe, WI 53566 | Suite 105 | Menomonee Falls, WI | |||||||||||
| BID ITEM | QTY | UNIT | DESCRIPTION | Onalaska, WI 54650 | Middleton, WI 53562 | 53051 | ||||||||||
| 1 | LS | Traffic Control | $13,521.00 | $14,500.00 | $21,300.00 | $30,695.00 | $22,800.00 | $12,000.00 | ||||||||
| 2 | LS | Clearing and grubbing | $21,626.00 | $38,000.00 | $36,000.00 | $40,238.00 | $29,000.00 | $48,000.00 | ||||||||
| 3 | 775 | LF | Pavement saw cutting | $1.80 | $1,395.00 | $3.00 | $2,325.00 | $1.00 | $775.00 | $2.25 | $1,743.75 | $2.00 | $1,550.00 | $2.00 | $1,550.00 | |
| 4 | 1800 | CU YD | Rock excavation | $39.00 | $70,200.00 | $6.00 | $10,800.00 | $67.00 | $120,600.00 | $82.50 | $148,500.00 | $1.00 | $1,800.00 | $50.00 | $90,000.00 | |
| 5 | 8000 | CU YD | Granular trench backfill | $13.00 | $104,000.00 | $6.50 | $52,000.00 | $9.95 | $79,600.00 | $11.00 | $88,000.00 | $12.00 | $96,000.00 | $26.00 | $208,000.00 | |
| 6 | 500 | TN | Crushed stone for unstable trench bottom | $14.50 | $7,250.00 | $10.00 | $5,000.00 | $15.00 | $7,500.00 | $14.75 | $7,375.00 | $18.00 | $9,000.00 | $12.00 | $6,000.00 | |
| 7 | 75 | LF | 36-in dia. ductile iron, epoxy lined, pressure Class 300, sewer pipe | $456.00 | $34,200.00 | $520.00 | $39,000.00 | $364.00 | $27,300.00 | $1,350.00 | $101,250.00 | $556.00 | $41,700.00 | $760.00 | $57,000.00 | |
| 8 | 3724 | LF | 36-in dia. sewer pipe | $155.50 | $579,082.00 | $158.00 | $588,392.00 | $168.00 | $625,632.00 | $187.00 | $696,388.00 | $233.00 | $867,692.00 | $297.00 | $1,106,028.00 | |
| 9 | 3898 | LF | 30-in dia. sewer pipe | $101.30 | $394,867.40 | $103.00 | $401,494.00 | $134.00 | $522,332.00 | $148.00 | $576,904.00 | $197.00 | $767,906.00 | $214.00 | $834,172.00 | |
| 10 | 170 | LF | 27-in dia. sewer pipe | $97.20 | $16,524.00 | $108.00 | $18,360.00 | $125.00 | $21,250.00 | $143.00 | $24,310.00 | $288.00 | $48,960.00 | $230.00 | $39,100.00 | |
| 11 | 40 | LF | 24-in dia. sewer pipe | $76.00 | $3,040.00 | $220.00 | $8,800.00 | $154.00 | $6,160.00 | $273.00 | $10,920.00 | $137.00 | $5,480.00 | $345.00 | $13,800.00 | |
| 12 | 150 | LF | 18-in dia. sewer pipe | $80.00 | $12,000.00 | $108.00 | $16,200.00 | $106.00 | $15,900.00 | $141.00 | $21,150.00 | $79.00 | $11,850.00 | $155.00 | $23,250.00 | |
| 13 | 30 | LF | 15-in dia. sewer pipe | $69.00 | $2,070.00 | $130.00 | $3,900.00 | $105.00 | $3,150.00 | $156.00 | $4,680.00 | $130.00 | $3,900.00 | $205.00 | $6,150.00 | |
| 14 | 10 | LF | 12-in dia. sewer pipe | $64.00 | $640.00 | $130.00 | $1,300.00 | $97.00 | $970.00 | $263.00 | $2,630.00 | $125.00 | $1,250.00 | $530.00 | $5,300.00 | |
| 15 | 85 | LF | 10-in dia. sewer pipe | $46.00 | $3,910.00 | $66.00 | $5,610.00 | $90.00 | $7,650.00 | $77.70 | $6,604.50 | $75.00 | $6,375.00 | $165.00 | $14,025.00 | |
| 16 | 25 | LF | 8-in dia. ductile iron, cement mortar lined, pressure Class 350 sewer pipe | $46.00 | $1,150.00 | $98.00 | $2,450.00 | $134.00 | $3,350.00 | $103.00 | $2,575.00 | $90.00 | $2,250.00 | $185.00 | $4,625.00 | |
| 17 | 177 | LF | 8-in dia. sewer pipe | $40.00 | $7,080.00 | $72.00 | $12,744.00 | $87.00 | $15,399.00 | $50.40 | $8,920.80 | $70.00 | $12,390.00 | $170.00 | $30,090.00 | |
| 18 | 15 | V FT | 96-in I.D. sanitary manhole (1 unit) | $625.00 | $9,375.00 | $520.00 | $7,800.00 | $658.00 | $9,870.00 | $809.00 | $12,135.00 | $825.00 | $12,375.00 | $750.00 | $11,250.00 | |
| 19 | 21 | V FT | 96-in I.D. inside drop sanitary manhole (1 unit) | $656.00 | $13,776.00 | $580.00 | $12,180.00 | $643.00 | $13,503.00 | $892.00 | $18,732.00 | $760.00 | $15,960.00 | $800.00 | $16,800.00 | |
| 20 | 17 | V FT | 84-in I.D. sanitary manhole (1 unit) | $567.00 | $9,639.00 | $460.00 | $7,820.00 | $548.00 | $9,316.00 | $655.00 | $11,135.00 | $675.00 | $11,475.00 | $720.00 | $12,240.00 | |
| 21 | 403 | V FT | 72-in I.D. sanitary manhole (21 units) | $146.00 | $58,838.00 | $346.00 | $139,438.00 | $405.00 | $163,215.00 | $639.00 | $257,517.00 | $510.00 | $205,530.00 | $400.00 | $161,200.00 | |
| 22 | 58 | V FT | 72-in I.D. inside drop sanitary manhole (4 units) | $463.00 | $26,854.00 | $401.00 | $23,258.00 | $475.00 | $27,550.00 | $642.00 | $37,236.00 | $685.00 | $39,730.00 | $630.00 | $36,540.00 | |
| 23 | 31 | V FT | 48-in I.D. sanitary manhole (2 units) | $214.00 | $6,634.00 | $260.00 | $8,060.00 | $256.00 | $7,936.00 | $199.00 | $6,169.00 | $330.00 | $10,230.00 | $290.00 | $8,990.00 | |
| 24 | 65 | LF | 6-in dia. PVC sanitary sewer lateral (4 units) | $39.00 | $2,535.00 | $98.00 | $6,370.00 | $45.00 | $2,925.00 | $48.80 | $3,172.00 | $68.00 | $4,420.00 | $230.00 | $14,950.00 | |
| 25 | 2 | Each | PVC sanitary sewer lateral cleanout | $550.00 | $1,100.00 | $400.00 | $800.00 | $250.00 | $500.00 | $185.00 | $370.00 | $750.00 | $1,500.00 | $150.00 | $300.00 | |
| 26 | 13 | Each | Field core sanitary sewer manhole for pipe connection | $1,678.00 | $21,814.00 | $1,200.00 | $15,600.00 | $475.00 | $6,175.00 | $984.00 | $12,792.00 | $1,300.00 | $16,900.00 | $900.00 | $11,700.00 | |
| 27 | LS | All work associated with by-pass sewerage pumping to maintain uninterrupted sanitary sewer service during construction of work | $16,340.00 | $68,000.00 | $35,553.00 | $20,237.00 | $38,000.00 | $22,500.00 | ||||||||
| 28 | LS | All work associated with connection of interceptor sewer to MMSD Pumping Station No. 17, including installation of bulkhead, coring pump station wall and connnection of 36-in dia. pipe | $49,830.00 | $46,000.00 | $25,357.00 | $18,997.00 | $33,000.00 | $62,000.00 | ||||||||
| 29 | LS | All work associated with raising existing 8-in dia. ductile iron water main | $3,075.00 | $4,300.00 | $5,375.00 | $2,949.00 | $4,500.00 | $8,000.00 | ||||||||
| 30 | 21000 | SY | Temporary seeding | $0.09 | $1,890.00 | $0.15 | $3,150.00 | $0.12 | $2,520.00 | $0.20 | $4,200.00 | $0.30 | $6,300.00 | $0.15 | $3,150.00 | |
| 31 | 21000 | SY | Mulching | $0.09 | $1,890.00 | $0.15 | $3,150.00 | $0.12 | $2,520.00 | $0.20 | $4,200.00 | $0.15 | $3,150.00 | $0.15 | $3,150.00 | |
| 32 | 3700 | LF | Furnish, install, maintain and remove, silt fence | $1.40 | $5,180.00 | $1.50 | $5,550.00 | $1.35 | $4,995.00 | $2.25 | $8,325.00 | $1.80 | $6,660.00 | $2.00 | $7,400.00 | |
| 33 | 8 | Each | Furnish, install, maintain and remove, WDOT Type D inlet protection | $95.00 | $760.00 | $200.00 | $1,600.00 | $155.00 | $1,240.00 | $35.00 | $280.00 | $180.00 | $1,440.00 | $300.00 | $2,400.00 | |
| 34 | 6 | Each | Furnish, install, maintain and remove, stone weeper | $363.00 | $2,178.00 | $450.00 | $2,700.00 | $500.00 | $3,000.00 | $450.00 | $2,700.00 | $1,030.00 | $6,180.00 | $2,900.00 | $17,400.00 | |
| 35 | 3 | Each | Furnish, install, maintain construction entrance | $524.00 | $1,572.00 | $1,000.00 | $3,000.00 | $1,100.00 | $3,300.00 | $700.00 | $2,100.00 | $700.00 | $2,100.00 | $2,500.00 | $7,500.00 | |
| 36 | 765 | SY | Turf reinforcement mat, Class III, Type C | $7.60 | $5,814.00 | $8.00 | $6,120.00 | $7.60 | $5,814.00 | $11.00 | $8,415.00 | $8.50 | $6,502.50 | $9.00 | $6,885.00 | |
| 37 | 1325 | SY | Furnish and install erosion mat, Class I, Type B | $1.05 | $1,391.25 | $2.00 | $2,650.00 | $1.55 | $2,053.75 | $1.90 | $2,517.50 | $1.80 | $2,385.00 | $1.00 | $1,325.00 | |
| 38 | 1 | Acre | Polymer Soil Stabilizer | $480.00 | $480.00 | $1,000.00 | $1,000.00 | $590.00 | $590.00 | $1,016.00 | $1,016.00 | $660.00 | $660.00 | $1,000.00 | $1,000.00 | |
| 39 | 1 | Each | Construct and remove earthen berm | $318.00 | $318.00 | $500.00 | $500.00 | $350.00 | $350.00 | $2,460.00 | $2,460.00 | $800.00 | $800.00 | $7,000.00 | $7,000.00 | |
| 40 | 15 | LF | Utility trench insulation | $10.00 | $150.00 | $12.00 | $180.00 | $25.00 | $375.00 | $5.20 | $78.00 | $10.00 | $150.00 | $7.00 | $105.00 | |
| 41 | 2000 | LF | Furnish, install, maintain and remove construction barrier fencing | $2.35 | $4,700.00 | $2.90 | $5,800.00 | $2.90 | $5,800.00 | $4.00 | $8,000.00 | $3.30 | $6,600.00 | $3.00 | $6,000.00 | |
| 42 | 65 | LF | Furnish and install 54-in dia. steel casing pipe, STA 12+05 to STA 12+70 | $2,170.00 | $141,050.00 | $1,946.00 | $126,490.00 | $1,789.00 | $116,285.00 | $1,399.00 | $90,935.00 | $1,770.00 | $115,050.00 | $2,100.00 | $136,500.00 | |
| 43 | 230 | LF | Furnish and install, 54-in dia. steel casing pipe, STA 74+10 to STA 76+40 | $2,240.00 | $515,200.00 | $2,513.00 | $577,990.00 | $2,112.00 | $485,760.00 | $2,707.00 | $622,610.00 | $2,360.00 | $542,800.00 | $3,000.00 | $690,000.00 | |
| 44 | 80 | LF | Furnish and install 48-in dia. steel casing pipe, STA 53+80 to STA 54+60 | $883.00 | $70,640.00 | $1,286.00 | $102,880.00 | $836.00 | $ 66,880.00 | $1,025.00 | $82,000.00 | $860.00 | $68,800.00 | $1,500.00 | $120,000.00 | |
| 45 | 7375 | LF | Abandon existing sanitary sewer | $6.00 | $44,250.00 | $10.50 | $77,437.50 | $6.15 | $45,356.25 | $6.35 | $46,831.25 | $7.00 | $51,625.00 | $12.00 | $88,500.00 | |
| 46 | 19 | Each | Abandon existing sanitary manhole | $571.00 | $10,849.00 | $800.00 | $15,200.00 | $500.00 | $9,500.00 | $195.00 | $3,705.00 | $920.00 | $17,480.00 | $1,000.00 | $19,000.00 | |
| 47 | 150 | LF | Remove existing sanitary sewer | $20.00 | $3,000.00 | $20.00 | $3,000.00 | $40.00 | $6,000.00 | $8.00 | $1,200.00 | $25.00 | $3,750.00 | $5.00 | $750.00 | |
| 48 | 4 | Each | Remove existing sanitary sewer manhole | $691.00 | $2,764.00 | $800.00 | $3,200.00 | $600.00 | $2,400.00 | $150.00 | $600.00 | $1,650.00 | $6,600.00 | $100.00 | $400.00 | |
| 49 | LS | Dane County highway permit | $587.00 | $500.00 | $150.00 | $190.00 | $780.00 | $500.00 | ||||||||
| 50 | - | All work associated with furnishing all materials and construction of concrete pipe cap | $1,345.00 | $2,800.00 | $3,500.00 | $1,243.00 | $1,100.00 | $4,700.00 | ||||||||
| 51 | 1 | Each | Utility location order (ULO) | $635.00 | $635.00 | $1,000.00 | $1,000.00 | $500.00 | $500.00 | $246.00 | $246.00 | $880.00 | $880.00 | $250.00 | $250.00 | |
| 52 | 2700 | TN | Crushed aggregate base course | $9.30 | $25,110.00 | $10.00 | $27,000.00 | $10.45 | $28,215.00 | $11.10 | $29,970.00 | $12.70 | $34,290.00 | $16.00 | $43,200.00 | |
| 53 | 40 | TN | Asphaltic concrete pavement, Type E-3, 19 mm binder course | $90.00 | $3,600.00 | $100.00 | $4,000.00 | $93.00 | $3,720.00 | $114.00 | $4,560.00 | $103.00 | $4,120.00 | $100.00 | $4,000.00 | |
| 54 | 25 | TN | Asphaltic concrete pavement, Type E-3, 12.5 mm surface course | $90.00 | $2,250.00 | $100.00 | $2,500.00 | $93.00 | $2,325.00 | $114.00 | $2,850.00 | $103.00 | $2,575.00 | $100.00 | $2,500.00 | |
| 55 | 60 | TN | Asphaltic concrete pavement, Type E-1, 19 mm binder course | $90.00 | $5,400.00 | $100.00 | $6,000.00 | $93.00 | $5,580.00 | $114.00 | $6,840.00 | $103.00 | $6,180.00 | $100.00 | $6,000.00 | |
| 56 | 185 | TN | Asphaltic concrete pavement, Type E-1, 12.5 mm surface course | $90.00 | $16,650.00 | $100.00 | $18,500.00 | $93.00 | $17,205.00 | $114.00 | $21,090.00 | $103.00 | $19,055.00 | $100.00 | $18,500.00 | |
| 57 | 220 | LF | 30-in wide concrete curb and gutter | $29.00 | $6,380.00 | $30.00 | $6,600.00 | $26.75 | $5,885.00 | $29.00 | $6,380.00 | $31.00 | $6,820.00 | $35.00 | $7,700.00 | |
| 58 | 70 | LF | 66-in wide concrete curb and gutter | $35.00 | $2,450.00 | $40.00 | $2,800.00 | $35.00 | $2,450.00 | $26.25 | $1,837.50 | $70.00 | $4,900.00 | $60.00 | $4,200.00 | |
| 59 | 175 | SF | 5-in thick, concrete sidewalk | $5.00 | $875.00 | $6.00 | $1,050.00 | $4.55 | $796.25 | $6.65 | $1,163.75 | $6.00 | $1,050.00 | $6.00 | $1,050.00 | |
|
|
|
|
||||||||||||||
| $2,371,723.65 | $2,574,848.50 | $2,657,208.25 | $3,142,868.05 | $3,254,305.50 | $4,076,625.00 | |||||||||||
| BID BOND | 5% | 5% | 5% | 5% | 5% | 5% | ||||||||||
| Addendum No. 1 | Yes | Yes | Yes | Yes | Yes | Yes | ||||||||||