Far East Interceptor Gaston Road Extension

 

 

 

 

 

 

 

 

 

 

 

Madison Metropolitan Sewerage District

 

 

 

 

 

 

 

 

 

 

 

Bid Tabulation: 22 May 2008, 2:00 p.m.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Capitol Underground

Globe Contractors

McHugh Excavating

R.G. Huston

Speedway Sand and Gravel

item

description

quantity

unit

unit price

ext price

unit price

ext price

unit price

ext price

unit price

ext price

unit price

ext price

1

traffic control

1

ls

21,200.00

21,200.00

4,600.00

4,600.00

3,708.00

3,708.00

5,732.00

5,732.00

10,000.00

10,000.00

2

dewatering

1

ls

120,000.00

120,000.00

114,000.00

114,000.00

95,300.00

95,300.00

53,370.00

53,370.00

50,000.00

50,000.00

3

saw cut asphalt pavement

84

lf

5.25

441.00

4.00

336.00

5.00

420.00

2.00

168.00

3.00

252.00

4

remove asphalt pavement

4030

sy

2.50

10,075.00

1.20

4,836.00

7.30

29,419.00

1.00

4,030.00

0.90

3,627.00

5

construction barrier fence

450

lf

3.15

1,417.50

5.00

2,250.00

3.00

1,350.00

2.00

900.00

2.50

1,125.00

6

21-in interceptor pipe

37

lf

525.00

19,425.00

450.00

16,650.00

158.00

5,846.00

82.00

3,034.00

150.00

>5,550.00

7

18-in interceptor pipe

1688

lf

158.00

266,704.00

273.00

460,824.00

126.00

212,688.00

95.00

160,360.00

130.00

219,440.00

8

infiltration/leakage tests

1

ls

2,900.00

2,900.00

1,500.00

1,500.00

2,110.00

2,110.00

966.00

966.00

4,000.00

4,000.00

9

deflection testing

1

ls

2,900.00

2,900.00

1,500.00

1,500.00

2,110.00

2,110.00

578.00

578.00

2,000.00

2,000.00

10

72-in concrete manholes

103

vf

375.00

38,625.00

375.00

38,625.00

394.00

40,582.00

410.00

42,230.00

466.00

47,998.00

11

30-in steel casing

40

lf

850.00

34,000.00

400.00

16,000.00

640.00

25,600.00

459.00

18,360.00

500.00

20,000.00

12

Select Sand Backfill

9800

ton

9.50

93,100.00

12.50

122,500.00

12.00

117,600.00

8.20

80,360.00

7.50

73,500.00

13

Foundation Stone

500

ton

13.50

6,750.00

25.00

12,500.00

21.50

10,750.00

17.50

8,750.00

25.00

12,500.00

14

geo-textile fabric for foundation stone

1200

sy

1.75

2,100.00

5.00

6,000.00

5.25

6,300.00

2.40

2,880.00

5.00

6,000.00

15

geo-textile fabric for pipe bedding

1200

sy

1.75

2,100.00

5.00

6,000.00

5.25

6,300.00

2.40

2,880.00

5.00

6,000.00

16

landscape restoration

1

ls

2,100.00

2,100.00

13,500.00

13,500.00

9,115.00

9,115.00

4,000.00

4,000.00

14,000.00

14,000.00

17

silt fence

2200

lf

1.40

3,080.00

1.50

3,300.00

1.35

2,970.00

1.85

4,070.00

1.50

3,300.00

18

stone construction entrance

1

ls

1,000.00

1,000.00

1,500.00

1,500.00

1,350.00

1,350.00

1,100.00

1,100.00

1,500.00

1,500.00

19

stone weepers

21

ls

325.00

6,825.00

200.00

4,200.00

525.00

11,025.00

320.00

6,720.00

140.00

2,940.00

20

Aggregate Base Course

2700

ton

10.25

27,675.00

11.60

31,320.00

10.00

27,000.00

10.30

27,810.00

10.00

27,000.00

21

asphaltic concrete pavement

525

 

 

 

 

 

 

 

 

 

 

 

 

19mm

 

ton

48.95

25,698.75

53.00

27,825.00

44.40

23,310.00

45.00

23,625.00

44.85

23,546.25

22

asphaltic concrete pavement 12mm

410

ton

51.85

21,258.50

57.00

23,370.00

44.85

18,388.50

45.40

18,614.00

45.30

18,573.00

23

asphaltic tack coat

205

gal

1.60

328.00

2.00

410.00

1.30

266.50

1.50

307.50

1.32

270.60

24

pavement marking

1350

lf

0.80

1,080.00

1.60

2,160.00

0.80

1,080.00

0.78

1,053.00

0.78

1,053.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Total

 

 

*

710,782.75

 

915,706.00

 

654,588.00

 

471,897.50

 

554,174.85